AGENDA ITEM
TO: HONORABLE MAYOR
AND MEMBERS OF THE CITY COUNCIL
FROM: CARLO TOMAINO
CITY MANAGER
BY: THOMAS BEKELE
PUBLIC WORKS DIRECTOR
SUBJECT:
title
RESOLUTION DECLARING FINAL ACCEPTANCE OF THE ADA CURB RAMP INSTALLATION PROJECT PURSUANT TO THE PUBLIC WORKS
CONTRACT WITH MAJ ENGINEERING
summary
Summary:
The ADA Curb Ramp Installation Project is part of the City’s ongoing efforts to enhance accessibility by providing ADA-compliant ramps and improving sidewalks throughout the City. On July 23, 2024, the City Council awarded a contract to MAJ Engineering for the construction of new ADA-compliant curb ramps at various locations within the City. This project is partially funded through a Community Development Block Grant (CDBG).
MAJ Engineering completed work for the ADA Curb Ramp Installation Project in accordance with the project specifications and to the satisfaction of the Public Works Department. Staff recommends the City Council adopt a resolution declaring the work performed by MAJ Engineering as complete and in conformance with the approved plans and specifications.
Strategic Plan Goal(s):
Goal No. 4 Infrastructure: Maintain and improve the City’s physical infrastructure, water system and recreational spaces.
recommendation
Recommendation:
Adopt a resolution, entitled:
A RESOLUTION OF THE CITY OF SIGNAL HILL, CALIFORNIA, DECLARING WORK TO BE COMPLETED IN CONFORMANCE WITH THE PLAN SPECIFICATIONS FOR THE ADA CURB RAMP INSTALLATION PROJECT IN ACCORDANCE WITH THE CONTRACT ENTERED INTO BETWEEN MAJ ENGINEERING INCORPORATED AND THE CITY OF SIGNAL HILL
body
Fiscal Impact:
The total cost of the ADA Curb Ramp Installation Project was $157,885, and utilized a combination of funding sources as detailed below:
• $68,952 from Fiscal Year 2024-25 CDBG funds (rolled over from FY 2023-24), Project No. 90.24009.
• $71,026 from Fiscal Year 2024-25 CDBG funds, Project No. 90.24009.
• $9,417 from the Fiscal Year 2024-25 CIP Reserve for ADA/Ramp Installation, Project No. 90.24008.
Additionally, on October 22, 2024, the City Council approved $8,490 in supplemental funding from the Fiscal Year 2024-25 CIP Reserve to address unforeseen conditions during construction.
Background and Analysis:
On July 23, 2024, the City Council awarded a Public Works contract to MAJ Engineering (MAJ) for construction of new ADA-compliant curb ramps at various locations throughout the City. The scope of work included the installation of ramps, adjustments to the existing manholes, the removal and reconstruction of approximately 750 linear feet of concrete cross gutters, reconstruction of curb and gutter, and approximately 650 square feet of sidewalk adjacent to the new ramps. The specific locations of the newly constructed ADA ramps are as follows:
1. Southeast corner of 19th Street and Junipero Avenue.
2. Northeast corner of 19th Street and Junipero Avenue.
3. Southwest corner of 20th Street and Junipero Avenue.
4. Southeast corner of 20th Street and Dawson Avenue.
5. Northwest corner of 20th Street and Stanley Avenue.
6. Northeast corner of 20th Street and Stanley Avenue
7. Southwest corner of 19th Street and Stanley Avenue
The contract term was established for 30 calendar days, with a not-to-exceed amount of $135,814 and a 10% contingency in accordance with the City’s Purchasing Guidelines. The complexity of the project, particularly the steep grades in areas adjacent to some of the ramps, resulted in unforeseen conditions that required additional work. On October 22, 2024, the City Council approved a change order in the amount of $8,490 to address these unforeseen conditions. The appropriation provided funding for the removal of additional curbs and gutters was necessary to achieve the required grades for proper installation.
The final contract amount, as approved by the Public Works Director, totaled $157,885. Following the completion of construction, the project underwent a final inspection and approval of final quantities, concluding successfully on October 28, 2024.
Based on the contractor's satisfactory performance and compliance with project specifications, staff recommends the City Council adopt the proposed resolution formally declaring the final acceptance of the project.